School Bond Information, April 1, 2003 Election
Propositions 9, 10, 11

Photo of Carol Comeau

On April 1, 2003, voters will decide whether to approve three school bond propositions to repair and renovate numerous schools districtwide and to construct a new high school in Eagle River and an administrative and training facility.

Thanks to statewide approval of Proposition C in the November election, we are eligible to receive 60 percent or 70 percent State reimbursement on all but a few of the bond projects. In all, the State will pay for 60 percent of the combined cost of all three propositions, subject to annual legislative appropriation. That's good news for local taxpayers.

Propositions 9, 10 and 11 were developed with the support of the Capital Request Advisory Committee (made up of parents, students and a good cross section of community members), the Anchorage School Board and the Anchorage Assembly. This rigorous public process helps ensure that critical needs throughout the district are addressed and that the community's investment in school facilities is protected.

Proposition 9 funds repair and major maintenance projects at most schools districtwide.

Proposition 10 is for an administrative and training facility that can house school support staff who are currently scattered across Anchorage in a variety of leased offices.

Proposition 11 continues major renovations at three high schools, funds renovations at two other schools, and funds construction of a new high school in Eagle River.

Please take a moment to learn about the projects and the costs, and, should you have any questions, don't hesitate to call our public affairs office at 742- 4153, or visit our Web site at www.asdk12.org. We are committed to providing you with the facts to make an informed decision on April 1.

Carol Comeau

 

(Documents provided here are PDF files and require the free Adobe Acrobat Reader to view. PDF icon. )

On December 9, 2002 the Anchorage School Board approved three bond propositions to go before the Anchorage voters in April 2003. The Anchorage Municipal Assembly approved the package on February 11, 2003.

Passed.

Proposition 9 - Major Maintenance, Equipment, and Land Acquisition, $41,790,000

Hammer and saw.
Bond overview
Failed Proposition 10 - Administrative and Training Facility, $42,000,000
Passed. Proposition 11 - School Renovations/Additions/Replacement, $125,540,000

ASD Memorandum #133  - 2003 General Obligation Bond Recommendations, Amended December 9, 2002

 

Passed.Proposition 9 — Major Repairs, Renewals, Equipment and Land

Projects

Estimated
Project Costs

Estimated Increase in
Annual Operations & Maintenance Costs

State
Reimbursement*

Mechanical Upgrades (21 schools) $ 3,990,000 $0 70%
Code/Hazmat/ADA Projects (districtwide) 2,365,000 0 70%
Electrical Projects (24 schools) 5,257,000 0 70%
Roof Replacements and Repairs (13 schools) 3,499,000 0 70%
Minor Building Renewal Projects (32 schools) 5,678,000 0 70%
Restroom Upgrades (19 schools) 2,083,000 0 70%
Traffic Safety/Site Upgrades (10 schools) 4,128,000 0 70%
Security Upgrades – Locks: Phase I (districtwide) 750,000 0 70%
Emergency Preparedness/Shelters (18 schools) 3,200,000 0 0%
10 School Buses 840,000 0 100%
(principal only)
Site Selection and Acquisition 10,000,000 0 0%
TOTAL $ 41,790,000 $0

 

FailedProposition 10 — Administrative and Training Facility

Projects

Estimated
Project Costs

Estimated Increase in
Annual Operations & Maintenance Costs

State
Reimbursement*

Administrative and Training Facility $ 42,000,000 $ 558,600 60%
TOTAL $ 42,000,000 $ 558,600

 

Passed.Proposition 11 — School Renovation and Construction

Projects

Estimated
Project Costs

Estimated Increase in
Annual Operations & Maintenance Costs

State
Reimbursement*

Bartlett High School – Phase 2 Construction
Renovate central area classrooms, build new science labs and 600-seat theater, upgrade core mechanical and electrical systems, improve south parking lot and administration areas
$ 26,940,000 $70,300 70%
Chester Valley Elementary School – Design Funding
Design renovation/addition of kindergarten classrooms, music classroom improvements, multipurpose room renovation, and other school improvement projects
750,000 0 60%
Chugach Optional School – Construction Funding
Build additional kindergarten classroom and art room, upgrade building systems, site improvements, renovate library and administrative areas
7,000,000 49,625 60%
New Eagle River Area High School – Construction Funding 51,000,000 2,129,575 60%
East High School – Phase 3 Construction, Phase 4 Design Funding
Build 700-seat theater, improve south entry and student parking area, upgrade performing arts, life skills and home economics classrooms
18,200,000 0 70%
Polaris K-12 School – Construction Funding
Build additional classrooms and addition to gym, upgrade mechanical and electrical systems, site improvements
18,600,000 164,900 60%
Sand Lake Elementary School – Design Funding
Design classroom addition, interior renovation and site improvements
750,000 0 60%
Service High School – Phase 2A Deferred Inflation, Phase 2B, 3 and 4 Design
Deferred construction inflation, design renovation/addition to two-story west classroom wing and art classrooms
2,300,000 0 70%
TOTAL $ 125,540,000. $2,414,400

*Subject to annual legislative appropriation.

 

Local Tax Impact

Passed.Proposition 9

$41,790,000

State reimbursement* $20,265,000
Estimated annual tax increase for every $100,000 of property value to retire debt $9.97

Estimated annual increase in tax cap for every $100,000 of property value to pay for operation and maintenance costs related to the proposed educational capital improvements

$0

FailedProposition 10

$42,000,000

State reimbursement* $25,200,000
Estimated annual tax increase for every $100,000 of property value to retire debt $7.50
Estimated annual increase in tax cap for every $100,000 of property value to pay for operation and maintenance costs related to the proposed educational capital improvements $2.98

Passed.Proposition 11

$125,540,000

State reimbursement* $80,068,000
Estimated annual tax increase for every $100,000 of property value to retire debt $20.29
Estimated annual increase in tax cap for every $100,000 of property value to pay for operation and maintenance costs related to the proposed educational capital improvements $12.87

Total–Prop. 9, 10, 11 combined

Estimated annual tax increase for every $100,000 of property value to retire debt $37.76
*Subject to annual legislative appropriation.

 

Bond Propositions 9, 10, 11 State vs. local share

 

Use our bond comment box to send comments or questions.If you have comments or questions regarding these bonds, call 907-742-4153 or e-mail us using our Bond comment box

 


Where to find more information
League of Women Voters of Anchorage prepares a Ballot Review
Municipality of Anchorage's web site has election information