2003-2004

2004-2005

2005-2006

2006-2007

2007-2008

2008-2009

Dimond            
Sand Lake Elementary School Design $750,000          
Sand Lake Elementary School Construction   $9,200,000        
Girdwood K-8 School Planning   $100,000        
Girdwood K-8 School Design     $500,000      
Girdwood K-8 School Construction       $4,000,000    
Bayshore Elementary School Design     $500,000      
Bayshore Elementary Construction       $4,000,000     
Gladys Wood Elementary School Design       $500,000    
Gladys Wood Elementary Construction         $4,000,000  
Klatt Elementary Design           $500,000

For projects beyond 2002-2003, the cost estimates will require verification and updating prior to submittal of funding requests, due to possible refinements in scope or inflation in construction costs.