2005-2006
2006-2007
2007-2008
2008-2009
2009-2010
2010-2011
Bartlett High School Phase 3A Construction (West Wing) and 3B-1 Design (1/2 of East Wing)   $12,000,000        
Bartlett High School Phase 3B-1 Construction (1/2 of East Wing) and Phase 3B-2 Design (1/2 of East Wing)     $7,000,000      
Bartlett High School Phase 3B-2 Construction (1/2 of East Wing) and Phase 4 Design (Gym/Cafeteria)       $8,000,000    
Bartlett High School Phase 4 Construction (Gym/Cafeteria) and Phase 5 Design (Parking/Fields)         $11,000,000  
Bartlett High School Phase 5 Construction (Parking/Fields)           $5,000,000
Chugiak High School Phase 4 Construction (House 4)   $4,000,000        
Chugiak High School Phase 5 Construction (Fields/Parking)     $4,000,000      
Dimond High School Gym/Pool Code Upgrade and Renewal   $4,000,000        
Dimond High School - Classroom Wing Addition         $10,000,000  
East High School Phase 4B-1 Construction (1/2 of SW House) and Phase 4B-2 Design (1/2 of SW House)   $6,750,000        
East High School Phase 4B-2 Construction (1/2 of SW House) and Phase 5-A Design (1/2 of SE House)     $6,750,000      
East High School Phase 5-A Construction (1/2 of SE House) and Phase 5-B Design (1/2 of SE House)       $7,750,000    
East High School Phase 5-B Construction (1/2 of SE House) and Phase 6 Design (NE House)         $8,000,000  
East High School Phase 6 Construction (NE House) and Phase 7 Design (Gym/Parking/Fields)           $11,750,000
Service High School Phase 3 Construction (Aux Gym/Boiler) and Phase 4 Design (Admin/IMC)   $10,000,000        
Service High School Phase 4 Construction (Admin/IMC) and Phase 5 Design (Cafeteria/Auditorium)     $12,000,000      
Service High School Phase 5 Construction (Cafeteria/Auditorium)       $25,000,000    
Service High School Phase 6 Design (Parking/Athletic Fields)         $1,000,000  
Service High School Phase 6 Construction (Parking/Athletic Fields)           $8,000,000
West High School Design     $1,000,000      
West High School Construction Phase 1       $6,000,000    
West High School Construction Phase 2         $6,000,000  
High School Totals $0 $40,750,000 $30,750,000 $46,750,000 $36,000,000 $24,750,000

High Schools | Middle Schools | Elementary Schools | Districtwide

Projects with attached dollar amounts will require funds to be obtained. After 2006-07, scope and costs are estimates and require verification. Both may be adjusted based on recommendations from Facilities resulting from preliminary design and facility audits.

Return to Table of Contents | Section IV

 