| Y (Yes) |
An applicable new component or upgrade is identified as required for the site |
| N (No) |
There are no new components or upgrades required for the site |
| U (Unknown) |
It is unknown if new components are required for the site |
| Y1 |
32nd Avenue Street enhancements are required. They include sidewalks, curb and lighting. School construction not in current CIP. |
| Y2 |
MOA Parks plan to develop sports fields prior to any school construction which is not in the current CIP. |
| Y3 |
C Street Construction Phase II - Dimond Boulevard to O'Malley Road completed 2006. It included lighting, drainage, landscaping, and pedestrian facilities. School construction not in current CIP. |
| Y4 |
94th Street will require construction for extension from Arctic Boulevard to King Street. School construction not in current CIP. |
| Y5 |
Coordination for extension of public sewer pending. |
| Y6 |
Coordination with MOA for proposed Anchorage Fire Department development. Coordination required for establishment of a
Maintenance Program for undeveloped portion of property. |
| Y7 |
Yosemite Drive and storm drainage issues require final resolution; construction scheduled for summer 2007. |
| Y8 |
Hiland Road/Glenn Highway Intersection will require upgrades; construction scheduled for summer 2007. |
| Y9 |
South Goldenview Drive will require upgrade to collector status with enhancements of sidewalk, curb and lighting. |
| Y10 |
Coordination required for all utilities and services. |
| Y11 |
Coordination for Glenn Highway development and drainage. |
| Y12 |
Coordinate with MOA Development Authority. |
| Y13 |
Coordinate for development of Creekside Parkway. Construction scheduled for summer 2007. |
| Y14 |
Coordination required for relocation of easement, and existing overhead lines. |