Anchorage School District logo ASD Online -- The Website of the Anchorage School District
Site Index | Site Options | Contact Us
Schools | Departments | About ASD | School Board | myASD

Capital Improvement Plan

Table 2: CIP Recommendations by Service Area (Bartlett)

Return to Table of Contents | Section IV

Bartlett | Chugiak | Dimond | East | Service | West | Districtwide | No priority

 

Priority

Projects by Attendance Area

2002-2003

2003-2004

2004-2005

2005-2006

2006-2007

2007-2008

  Bartlett:            
6 Bartlett High School Phase 2 Design $1,900,000          
24 Bartlett High School Phase 2 Construction   $17,200,000        
30 Chester Valley Elementary Addition and Renovation: EED Matching Funds   $4,000,000        
38 Muldoon Middle School Construction     $51,000,000      
41 Bartlett High School Phase 3 Design     $2,000,000      
62 Bartlett High School Phase 3 Construction       $17,700,000    
82 Bartlett High School Phase 4 Design         $1,600,000  
100 Bartlett High School Phase 4 Construction           $14,200,000

For projects beyond 2002-2003, the cost estimates will require verification and updating prior to submittal of funding requests, due to possible refinements in scope or inflation in construction costs.

Bartlett | Chugiak | Dimond | East | Service | West | Districtwide | No priority

Return to Table of Contents | Section IV


Anchorage School District logo