Capital Improvement Plan, 2003-2009
Table 1: CIP Recommendations by Year, 2003-2004
Return to Table of Contents |
Section IV
2003-04 | 2004-05
| 2005-06 | 2006-07 |
2007-08 | 2008-09 | No
Priority | Total
|
Priority |
Projects |
2003-2004 |
2004-2005 |
2005-2006 |
2006-2007 |
2007-2008 |
2008-2009 |
| 1 |
Service High School Phase 2A Deferred Inflation, Phase 2B Design, Phases 3 and
4 Preliminary Design |
$2,300,000 |
|
|
|
|
|
| 2 |
Bartlett High School Phase 2 Construction |
$26,940,000 |
|
|
|
|
|
| 3 |
East High School Phase 3 Construction and Phase 4 Design |
$18,200,000 |
|
|
|
|
|
| 4 |
Eagle River High School Construction |
$51,000,000 |
|
|
|
|
|
| 5 |
Chugach Optional School Construction |
$7,000,000 |
|
|
|
|
|
| 6 |
Polaris K-12 Construction |
$18,600,000 |
|
|
|
|
|
| 7 |
Chester Valley Elementary Addition and Renovation Design |
$750,000 |
|
|
|
|
|
| 8 |
Sand Lake Elementary School Design |
$750,000 |
|
|
|
|
|
| 9 |
Districtwide Mechanical Upgrades |
$3,990,000 |
|
|
|
|
|
| 10 |
Districtwide Code/Hazmat/ADA Projects |
$2,365,000 |
|
|
|
|
|
| 11 |
Districtwide Electrical Projects |
$5,257,000 |
|
|
|
|
|
| 12 |
Districtwide Roof Replacement and Repairs |
$3,499,000 |
|
|
|
|
|
| 13 |
Districtwide Minor Building Renewal Projects |
$5,678,000 |
|
|
|
|
|
| 14 |
Districtwide Restroom Upgrades |
$2,083,000 |
|
|
|
|
|
| 15 |
Districtwide Traffic Safety/Site Upgrades |
$4,128,000 |
|
|
|
|
|
| 16 |
Security Upgrades- Locks: Phase 1 |
$750,000 |
|
|
|
|
|
| 17 |
Administrative and Training Facility |
$42,000,000 |
|
|
|
|
|
| 18 |
Emergency Preparedness |
$3,200,000 |
|
|
|
|
|
| 19 |
Replacement School Buses |
$840,000 |
|
|
|
|
|
| 20 |
Site Selection and Acquisition |
$10,000,000 |
|
|
|
|
|
2003-04 | 2004-05 |
2005-06 | 2006-07 | 2007-08
| 2008-09 | No Priority |
Total
For projects beyond 2003-2004, the cost estimates will require
verification and updating prior to submittal of funding requests, due to
possible refinements in scope or inflation in construction costs.
Return to Table of Contents |
Section IV
|
 |
|