2002-2003

2003-2004

2004-2005

2005-2006

2006-2007

2007-2008

Service            
Service High School Phase 2A Deferred Inflation, Phase 2B Design, Phases 3 and 4 Preliminary Design $2,300,000          
Rabbit Creek Elementary School Design   $500,000        
Rabbit Creek Elementary Construction     $11,300,000      
Abbott Loop Elementary School Design     $500,000      
Service High School Phase 2B Construction and Phase 3 Design     $14,500,000      
Service High School Phase 3 Construction and Phase 4 Design       $14,000,000    
Abbott Loop Construction       $3,500,000    
O'Malley Elementary School Design       $500,000    
Huffman Elementary School Design         $500,000  
Service High School Phase 4 Construction         $16,000,000  
O'Malley Elementary Construction         $4,000,000  
Spring Hill Elementary Design           $500,000
Huffman Elementary School Construction           $4,000,000
Bear Valley Elementary Design           $500,000

For projects beyond 2002-2003, the cost estimates will require verification and updating prior to submittal of funding requests, due to possible refinements in scope or inflation in construction costs.

 