Projects by Attendance Area

2004-2005

2005-2006

2006-2007

2007-2008

2008-2009

2009-2010

Bartlett:            
Bartlett High School Phase 3 Design $2,000,000          
Chester Valley Elementary Construction $15,000,000          
Muldoon Middle School Construction $52,000,000          
Bartlett High School Phase 3A Construction and 3B Design   $11,000,000        
Bartlett High School Phase 3B Construction     $12,000,000      
Bartlett High School Phase 4 Design       $1,200,000    
Bartlett High School Phase 4 Construction         $12,000,000  
Susitna Elementary School Design           $600,000