Capital Improvement Plan, 2005-2011

Table 2A: CIP Recommendations by Attendance Area, Bartlett

Return to Table of Contents | Section IV

Bartlett | Chugiak | Dimond | East | Service | South | West | Districtwide

Projects by Attendance Area

2005-2006
2006-2007
2007-2008
2008-2009
2009-2010
2010-2011
Chester Valley Elementary Construction- Proposed EED Grant ($6,700,000)          
Chester Valley Elementary Construction-Match of EED Grant and Gym/Art Room Addition   $4,900,000        
Bartlett High School Phase 3A Construction (West Wing) and 3B-1 Design (1/2 of East Wing)   $12,000,000        
Bartlett High School Phase 3B-1 Construction (1/2 of East Wing) and Phase 3B-2 Design (1/2 of East Wing)     $7,000,000      
Bartlett High School Phase 3B-2 Construction (1/2 of East Wing) and Phase 4 Design (Gym/Cafeteria)       $8,000,000    
Bartlett High School Phase 4 Construction (Gym/Cafeteria) and Phase 5 Design         $11,000,000  
Bartlett High School Phase 5 Construction (Parking/Fields)           $5,000,000

Bartlett | Chugiak | Dimond | East | Service | South | West | Districtwide

Projects with attached dollar amounts will require funds to be obtained. After 2006-07, scope and costs are estimates and require verification. Both may be adjusted based on recommendations from Facilities resulting from preliminary design and facility audits.