Capital Improvement Plan, 2006-2012

Table 2A: CIP Recommendations by Attendance Area, Chugiak/Eagle River

Return to Table of Contents | Section IV

Bartlett | Chugiak/Eagle River | Dimond | East | Service | South | West | Districtwide

Projects by Attendance Area

2006-2007
2007-2008
2008-2009
2009-2010
2010-2011
2011-2012
Chugiak High School Phase 4 Construction (House 4) and Phase 5 Design $12,500,000          
Eagle River Elementary School Planning   $70,000        
Chugiak High School Phase 5 Construction (Fields/Parking)   $4,200,000        
Gruening Middle School Planning     $125,000      
Eagle River Elementary School Design     $1,030,000      
Gruening Middle School Phase 1 Design       $1,545,000    
Eagle River Elementary School Construction       $10,300,000    
Birchwood ABC School Planning         $70,000  
Gruening Middle School Phase 1 Construction and Phase 2 Design         $5,150,000  
Birchwood ABC School Design           $800,000
Gruening Middle School Phase 2 Construction           $5,150,000

Bartlett | Chugiak/Eagle River | Dimond | East | Service | South | West | Districtwide

Projects with attached dollar amounts will require funds to be obtained. After 2007-08, scope and costs are estimates and require verification. Both may be adjusted based on recommendations from Facilities resulting from preliminary design and facility audits.