Capital Improvement Plan, 2007-2013

Table 2B: CIP Recommendations by Level of School, Elementary Schools

Return to Table of Contents | Section IV

High Schools | Middle Schools | Elementary Schools | Districtwide

Elementary Schools

2007-2008
2008-2009
2009-2010
2010-2011
2011-2012
2012-2013
Airport Heights Elementary School Planning           $75,000
Bayshore Elementary School Planning           $75,000
Chester Valley Elementary Construction   $15,200,000        
Eagle River Elementary School Planning           $75,000
Girdwood K-8 School Planning
Partial Funding by Senate Bill; $49,000
$0          
Girdwood K-8 School Design     $525,000      
Girdwood K-8 School Construction       $8,650,000    
Gladys Wood Elementary School Planning
Funded by Senate/House Bill; $65,000
$0          
Gladys Wood Elementary School Design       $1,075,000    
Gladys Wood Elementary School Construction         $10,750,000  
Inlet View Elementary School Design       $780,000    
Inlet View Elementary School Construction         $7,600,000  
Mt. View School Elementary Planning           $75,000
New Southwest Anchorage Area Elementary School Planning       $110,000    
New Southwest Anchorage Area Elementary School Construction         $20,000,000  
O'Malley Elementary School Planning           $75,000
Rabbit Creek Elementary School Design         $1,300,000  
Rabbit Creek Elementary School Construction           $12,750,000
Sand Lake Elementary School Construction   $13,600,000        
Turnagain Elementary School Design         $975,000  
Turnagain Elementary School Construction           $12,750,000
Elementary School Totals $0 $28,800,000 $525,000 $10,615,000 $40,625,000 $25,875,000

High Schools | Middle Schools | Elementary Schools | Districtwide

Projects with attached dollar amounts will require funds to be obtained. After 2008-09, scope and costs are estimates and require verification. Both may be adjusted based on recommendations from Facilities resulting from preliminary design and facility audits.