Phase II of the Construction Project
While construction of Clark Middle School actually began in Fall 2007, February 25, 2008 was an exciting day on the construction site of Clark Middle School. The steel arrived and construction began to show a great deal of movement. Davis Construction and their dynamic crew started erecting the steel girding on the school. This summer, the structure will have a new roof and will be closed in so crews can start on the extensive internal work. Soon, Mrs. Williams will have new halls to walk and then students to fill them.
Click on the image below to watch a slide show of the construction. (Requires Flash Player 7)

Project Status Report - December 1, 2008
| Project name |
Clark Middle School replacement |
| Project description |
Replacement school |
| Project budget |
Original: $65,550,000 |
Current: $65,550,000 |
| Construction status |
Interior wall, electrical and mechanical work is all progressing well. The interior work and painting has started on level three. Casework, light fixtures, data cabling and ceiling grid are being installed on levels one and two. |
| Construction contract status |
Original contract |
Change orders to date |
Change order % |
Completion % |
| Davis Constructors & Engineers, Inc. (7C00403) |
$52,140,035 |
$0 |
0% |
68% |
| Schedule Status |
Original completion date |
Completion date from prior report |
Change from prior report |
New completion date |
| |
July 10, 2009 |
July 10, 2009 |
|
|
Bond information
Review the history of bond information for Clark Middle School »
|